Reduced cooling energy consumption by providing new Chillers in nine buildings. For each of those buildings, GMI provided Design and Engineering
FAA SERVER – BLDG 10B
Installed new critical server room with 40 server racks, UPS system, 400KW generator, 100 ton Air Cooled Chiller, 9 Liebert in-row cooling units, fire
FORT BELVOIR – BLDG 201
Updating Building 201 included drywall, paint, doors, floors and ceilings. Renovated HVAC System. Furnished & installed 7 Indoor central station
CENSUS BUREAU
Assisted in the design of the HVAC system; Furnished and installed new 20 ton Air Handler Unit with 5 VAV's; Established all new Control systems
FORT BELVOIR 1400 DECENTRALIZATION
Removed 18 buildings from central heating plant and installed boilers, unit heaters, air handling units, flues, roofing, concrete & demolition